AGSI Storage Inventory ALSI LNG Inventory UMM Inside Information UMM detail - 22062321X000000001075A496_002
Message ID:
22062321X000000001075A496_002
Publication Date/Time:
2022-06-23 11:20:11 UTC
 
Market Participant:
Nederlandse Aardolie Maatschappij B.V.
Market Participant Code:
A0005524K.NL
 
Balancing Zone:
Dutch Balancing zone
Balancing Zone Code:
21YNL----TTF---1
 
Affected Asset or Unit:
NORG-NAM
Affected Asset or Unit Code:
21W000000000015A
 
Event Start:
2022-06-23 10:00:00 UTC
Event Stop:
2022-06-23 19:00:00 UTC
Event Status:
Active
Type of Event:
Injection unavailability
 
Direction:
Unavailable Capacity:
267.000000000 GWh/d
Available Capacity:
134.000000000 GWh/d
Technical Capacity:
401.000000000 GWh/d
 
Type of Unavailability:
Unplanned
Reason for the Unavailability:
Due to the high outdoor temperature the cooling water temperature is to high. Therefore 1 compressor is down.
rev2: 2 compressors down in stead of 1, wrong in first text, capacities were correct.
 
Remarks:
In the evening the temperature will be low enough to start the compressor.
Message ID:
22062321X000000001075A496_001
Publication Date/Time:
2022-06-23 11:00:12 UTC
 
Market Participant:
Nederlandse Aardolie Maatschappij B.V.
Market Participant Code:
A0005524K.NL
 
Balancing Zone:
Dutch Balancing zone
Balancing Zone Code:
21YNL----TTF---1
 
Affected Asset or Unit:
NORG-NAM
Affected Asset or Unit Code:
21W000000000015A
 
Event Start:
2022-06-23 10:00:00 UTC
Event Stop:
2022-06-23 19:00:00 UTC
Event Status:
Active
Type of Event:
Injection unavailability
 
Direction:
Unavailable Capacity:
267.000000000 GWh/d
Available Capacity:
134.000000000 GWh/d
Technical Capacity:
401.000000000 GWh/d
 
Type of Unavailability:
Unplanned
Reason for the Unavailability:
Due to the high outdoor temperature the cooling water temperature is to high. Therefore 1 compressor is down.
 
Remarks:
In the evening the temperature will be low enough to start the compressor.