UMM detail - 25043021X000000001403J001_005
- Message ID:
- 25043021X000000001403J001_005
- Publication Date/Time:
- 2025-06-09 11:34:01 UTC
- Market Participant:
- Deutsche Energy Terminal GmbH
- Market Participant Code:
- 21X000000001403J
- Event Start:
- 2025-05-16 14:00:00 UTC
- Event Stop:
- 2025-08-15 04:00:00 UTC
- Event Status:
- Active
- Remarks:
- Terminal commissioning activities began on May 23rd at 16:00 LT. The next cargo is scheduled for June 13th.
Full commissioning is expected to be completed by mid-August.
- Message ID:
- 25043021X000000001403J001_004
- Publication Date/Time:
- 2025-05-22 15:32:57 UTC
- Market Participant:
- Deutsche Energy Terminal GmbH
- Market Participant Code:
- 21X000000001403J
- Event Start:
- 2025-05-16 14:00:00 UTC
- Event Stop:
- 2025-08-15 04:00:00 UTC
- Event Status:
- Active
- Remarks:
- Terminal commissioning activities are set to begin on May 23rd, 16:00 LT, with a send-out rate of 1.3 GWh/hr until June 7th. During this period, all gas injected into the OGE transmission system will be directed exclusively to the Etzel UGS.
Full commissioning is expected to be completed by mid-August.
- Message ID:
- 25043021X000000001403J001_003
- Publication Date/Time:
- 2025-05-16 07:07:30 UTC
- Market Participant:
- Deutsche Energy Terminal GmbH
- Market Participant Code:
- 21X000000001403J
- Event Start:
- 2025-05-16 14:00:00 UTC
- Event Stop:
- 2025-08-15 04:00:00 UTC
- Event Status:
- Active
- Remarks:
- The first commissioning LNG cargo for the Wilhelmshaven 2 LNG terminal is scheduled for delivery today.
The LNG carrier's operations are expected to last 5–7 days.
Terminal commissioning activities are set to begin on May 24th, with a send-out rate of 31.2 GWh/d until June 7th. During this period, all gas injected into the OGE transmission system will be directed exclusively to the Etzel UGS.
Full commissioning is expected to be completed by mid-August.
- Message ID:
- 25043021X000000001403J001_002
- Publication Date/Time:
- 2025-05-12 12:17:31 UTC
- Market Participant:
- Deutsche Energy Terminal GmbH
- Market Participant Code:
- 21X000000001403J
- Event Start:
- 2025-05-16 14:00:00 UTC
- Event Stop:
- 2025-08-15 04:00:00 UTC
- Event Status:
- Active
- Remarks:
- The first commissioning LNG cargo for Wilhelmshaven 2 LNG terminal is scheduled for delivery on May 16th.
Terminal commissioning activities are expected to commence on May 24th. No gas send-out to the grid will occur before this date.
Full commissioning is expected to be completed by mid-August.
- Message ID:
- 25043021X000000001403J001_001
- Publication Date/Time:
- 2025-04-30 09:55:14 UTC
- Market Participant:
- Deutsche Energy Terminal GmbH
- Market Participant Code:
- 21X000000001403J
- Event Start:
- 2025-05-17 02:00:00 UTC
- Event Stop:
- 2025-08-15 04:00:00 UTC
- Event Status:
- Active
- Remarks:
- The first commissioning LNG cargo for Wilhelmshaven 2 LNG terminal is scheduled for delivery on May 17th.
Terminal commissioning activities are expected to commence on May 24th. No gas send-out to the grid will occur before this date.
Full commissioning is expected to be completed by mid-August.